Successful Q-REG start-up via remote commissioning at Gerdau, Divinopolis plant, Brazil

Two weeks and only one specialist to achieve the Final Acceptance Certificate


Successful Q-REG start-up via remote commissioning at Gerdau, Divinopolis plant, Brazil

COVID-19 did not slow down the start-up of new Q-REG® (Electrodes Regulation System) for Ladle Furnace at Gerdau, in Divinopolis plant – MG – Brazil.

Communication and I/O tests have been executed using remote connection to safeguard as much as possible everyone's health during the commissioning.

Just the limited presence of a specialist for the latest few days has been enough to complete the tuning of the system and to achieve the Final Acceptance Certificate.

The great cooperation between Gerdau and Danieli Automation teams made a very fast and effective technological upgrade possible, including an automation and hydraulic systems upgrade.

 